Key Projects |
|
|
|
|
|
| Project Name: |
| The Concession Project of natural gas in the East New District of YiZhuang Road |
| Project Owner: |
| Beijing Municipality |
Project brief
The East New District of YiZhuang Road is located at the east of the YiZhuang secondary planet city, at the north of the JingJinTang Highway, and its north is the east prolonged line on the north loop line of the exploitation district, its east is the planned TongHui main drainage channel, its south is the LiangShui River, its west is the JingJinTang Highway. The total planning area is 13.23 square kilometers, among which the total architectural area is 9,071,800m3. The predicted natural gas consumption of the district will reach 0.226 billion m3 per-year, and even 109700 m3 per-hour at the peak of consumption.
The scheme of the natural gas supplying of the district is: in the near future, the gas is obtained from the A modulated- pressure station with 1.0 MPa secondary high-pressure located at the southwest of the YiZhuang east district by the natural gas emergency Project in 2004, and a new secondary high-pressure modulation station(or the modulated-pressure box) will be constructed to supply gas for the new district of the road east. In the far future, there will be another two secondary high-pressure modulation station(or the modulated-pressure box) in the district to meet the requirement of increasing load. The consumer supplying within the district will adopt the grade one pressure of the middle-pressure supplying mode, which means the middle-low pressure modulation stations are not installed, and the middle-pressure natural gas will be delivered directly to the modulated-pressure box in font of the consumers' building with the pipes net of the district.
The investors can design the construction scheme according to the required scale and content of the Project and their own characteristics.
total investment
The total investment of the Project is about 0.133 billion yuan, among which the construction investment is 0.130 billion yuan and the floating capital is 3,000,000 yuan. In the construction investment: the capital asserts is 110,350,000 yuan, the immateriality and handing over capital charge is about 14,000,000 yuan and the prearrangement charge is 6,220,000 yuan.
Project content
The Project will select the licensed operators to invest, construct and manage the natural gas facilities of the district by the means of public bidding. During the Concession, the investors will get the investment return by charging the consumption fees to the consumers.
Project condition and guarantee
The price of natural gas: the pumping purchase price is 1.19 yuan per m3, the price of the retailed gas charged by the licensed operator and the classification standard of the consumers are executed according to the prescription of Jing Price (business) letter [2003]141 document enacted by the price bureau of the city.
* The Concession time limit: the operation time limit of the Project is restricted as 25 years( including 3 years of construction) temporarily.
* Promise monopolization of the operation right during the whole Concession period.
* Support and pay the fees ahead for the dismantling and installing for the land use of the Project.
* Arrange the licensed operators and the gas company to endorse the pumping purchase agreement.
* Carry out the Project construction within the general Contact scheme of the exploitation district.
* The consumers enjoy the consistent price of the natural gas in the city.
* The price of gas used in industry, heating and other conditions can be unlocked in the situation of according with the description of relative policies and the reasonable benefit got by the investors.
investor's condition
The investor can be the independent legal person, or the combo consists of legal entities. And the investor should have the experience of investment, construction, and management on the Projects of piping natural gas of the towns, and operate successfully above three years without severe incident. The investor will have sufficient cash or financing capacity to pay the money required by the establishment of the Project, and will be capable of raise all of the required money of the Project by the means of entire capital stock or debt financing.
Time schedule
* From April 15th to April 22nd , the prejudication of the investors' qualification
* From April 23rd to April 29th , release the bidding documents
* April 30th , the bidders make the locale review
* From May 8th to May 9th , questions answering before bidding
* From May 10th -May 24th ,the bidders prepare and hand in the bidding documents.
* From May 25th to May 31st, constitute the bidding evaluation committee and evaluate the bids.
* From June 1st to the July 1st , the bidding side and the successful bidder candidate negotiate and Contact.
Project organizer
The director branch of the department is in charge of organizing bidding committee and in charge of the bidding instructing work of the Project. After the licensed operator is selected, the government and the Concession company will subscribe the .
|
| |
|
|
| |
|
|